NAS Pt. Mugu – Install Retaining Sea Wall

NAS Pt. Mugu – Install Retaining Sea Wall

• Task: Reinforce deteriorated existing sea wall.

• Reason: The existing sea wall was deteriorated and failing.

• Process: Cut the existing asphalt, and excavated for the new wall footing. Installed steel to reinforce the concrete. Poured concrete for the footing, and “shotcrete” for the upright wall.